Blog 79 Caveator who adopted conflicting positions left unsatisfied.

Colony Constructions Pty Ltd v Zain Homes Pty Ltd & Ors [2023] VSC 529, Ginnane J.

This short case is an illustration of the importance, when faced with a serious breach of contract by the other party, of either accepting the breach and thereby terminating the contract or declining to accept the breach and asserting your intention to go on with the contract.  Confusion between these options possibly contributed to this caveator claiming the wrong interest and grounds.  The first defendant was a purchaser under a contract which did not settle on the due date, following which the vendor served a 14 day Notice of Default and Rescission and the third defendant (invalidly because it was the nominee transferee) served a 14 day Default Notice based on alleged deterioration to the premises and an inadequate planning permit.  Following expiry of both Notices the first defendant: wrote stating that the alleged breach had not been rectified and that the contract was at an end; and caveated claiming an interest as chargee on the grounds of implied, resulting or constructive trust.  On the plaintiff vendor applying under the Transfer of Land Act s. 90(3) to remove the caveat the purchaser adopted conflicting positions: its director deposed that “the caveat was lodged to protect my interests in the property namely the return of the deposit and or to purchase the property”; its counsel submitted that its conduct demonstrated that it wished to settle the contract; and in written submissions the purchaser relied on the right of rescission under ss. 32K and 34 of the Sale of Land Act 1962.  Ginnane J. held it arguable that the vendor had breached the contract, raising an arguable issue of whether it had the right to serve its Notice, but as the caveat had not claimed an interest as a purchaser the caveator only arguably had asserted an equitable lien for the return of the deposit.  Accordingly, appropriate relief was removal of the caveat with the deposit to be held in the vendor’s solicitor’s trust account.   His Honour stated –

“I have noted and considered the emphatic submissions of the defendant’s counsel that if the caveat is removed it will lose its right to settle the property, a right which may be later established.  However, … I can only consider the claims described in the caveat and they do not rely on the contract of sale …”

The facts were –

  • On 18 February 2022 the plaintiff entered a contract to sell a property to the first defendant for $727,270, with a deposit of $77,000 which was paid, due for settlement on 18 February 2023. The conditions included that: the “contract is subject to the vendor providing the purchaser endorsed plans and permits” (Special Condition 6); the vendor must deliver the property to the purchaser at settlement in the same condition as it was in on the day of sale, except for fair wear and tear (General Condition 24.2).
  • The first defendant nominated the third defendant as transferee.
  • A planning permit was issued allowing partial demolition of a building and erection of six units.
  • The contract did not settle on the due date. On 20 February 2023 the vendor served a 14 day Notice of Default and Rescission describing the default as “failure to settle per the terms of the contract”.   On the same day the nominee served a Default Notice describing the default as “non-compliance of general condition 24.2 & special condition regarding endorsed planning permit” and stating that the purchaser intended to exercise its rights unless within 14 days the default was remedied and legal costs were paid.
  • On 9 March the first defendant by its lawyers emailed the plaintiff’s conveyancer stating that the alleged breach had not been rectified and that the contract was at an end.  It also caveated claiming an interest as chargee on the grounds of implied, resulting or constructive trust.
  • The plaintiff resold the property and applied under the Transfer of Land Act s. 90(3) to remove the caveat. The first defendant’s director deposed to damage to the property alleged to have occurred after the date of the contract.  The first defendant submitted that the plans provided did not contain a valid planning permit as stipulated in Special Condition 6 so as to enable performance of the building works.
  • The plaintiff argued that the first defendant had adopted conflicting positions concerning whether the contract was still on foot. The first defendant submitted that its conduct demonstrated that it wished to settle the contract, but its director also deposed that “the caveat was lodged to protect my interests in the property namely the return of the deposit and or to purchase the property”.  In written submissions the first defendant also relied on the right of rescission under ss. 32K and 34 of the Sale of Land Act 1962.

Ginnane J. ordered removal of the caveat on condition that the deposit was held in the vendor’s solicitor’s trust account until final determination of the proceeding or further order and on condition that the purchaser counterclaimed to substantiate its claim to the deposit –

  1. The third defendant’s Notice was invalid because it was a nominee who could not exercise rights under the contract. [7]
  2. The first defendant’s contentions that the plaintiff had breached the contract in failing to provide a valid planning permit and because of damage to the property raised an arguable issue as to whether the plaintiff had the right to serve its Notice. [8]
  3. Although the caveat had not claimed an interest as a purchaser (the claim of an implied, resulting or constructive trust did not claim an estate or interest arising under the contract) the caveator had established a serious question to be tried of an interest in the land in the form of an equitable lien for the return of the deposit – the caveat asserted such an interest when it referred to the first defendant’s interest as a chargee. [10]-[11]
  4. The first defendant’s arguable interest in the $77,000 deposit could be protected by a removal of the caveat on condition as stated above. The balance of convenience favoured that course.  This removal would deprive the first defendant of its right (which may later be established) to settle the contract but the caveat had not relied on the contract. [12]-[13]

Philip H. Barton

Owen Dixon Chambers West

Tuesday, December 19, 2023

Blog 78 Mortgage and caveat securing solicitor’s fees survive.

Dixon (as trustee of the bankrupt estate of Toufic Sassine) v Lennon & Anor [2023] VSC 426, Barrett AsJ.

This is the first case covered by this Blog involving a solicitor’s costs agreement.  The agreement was held non-binding for breach of the Legal Profession Uniform Law (Vic) but nonetheless a charge and all monies mortgage in respect of the solicitor’s costs were valid, a term in the deed of charge permitting the solicitor to lodge a caveat.   The facts were as follows –

  • The first defendant (Lennon) was the principal and registered proprietor of Lennon Lawyers being a registered firm pursuant to the Business Names Registration Act 2011(Cth).
  • Toufic Sassine (Sassine) and Andrew Sassine (the Sassines) were registered as tenants in common in equal shares of certain land (the Land) encumbered by a registered mortgage to a bank.
  • On or around 20 November 2020 (as deposed by Lennon on 22 November 2022) the firm was retained to act for the Sassine family and their related corporate entities and a Disclosure Statement and Costs Agreement (costs agreement) bearing the date of 20 November 2020 was provided to the Sassines. Lennon exhibited to his affidavit a copy of the costs agreement which identified the law practice as Lennon Lawyers, stated that the clients were Sassine and Angela Sassine, and stated that the matter was “(SUP) Our Ref: 20/0723” with no description of the legal services to be provided.  The document provided that “it may be accepted by writing to us indicating your acceptance, by returning a signed copy of this document as provided in the Acknowledgement at the end of this document or by continuing to give us instructions in this matter”.
  • Lennon also deposed that to secure payment for legal services for the Sassine family it authorised Sassine and Andrew Sassine to execute a deed of charge in favour of the firm over their interest in the Land, and that a deed of charge and mortgage were executed accordingly.
  • On 20 November 2020 a deed of charge (the charge) was executed between Lennon Lawyers and the Sassines. It inter alia:
    • recited that the firm had provided and would provide professional services (the Services) to the Sassine family and their corporate entities;
    • provided that the firm had provided and would provide the Services up to the value of $100,000 (cl. 1);
    • provided that the Sassines hereby charged as security for the Services all their interest in the Land, agreed to execute a mortgage, and agreed that the firm “shall register a caveat over the said property to better secure the Services in accordance with this Deed” (cl. 2).
  • On 24 November 2020 Lennon caveated claiming an interest as chargee on the grounds of an agreement with the registered proprietor(s) dated 20 November 2020.
  • On 30 November 2020 a mortgage was executed over the Land by the Sassines as mortgagors and Lennon as mortgagee. This inter alia provided –
    • the mortgagor mortgaged the land to the mortgagee “as security for the debt or liability described in the terms and conditions set out or referred to in this mortgage”;
    • under the heading “Terms and Conditions of this Mortgage” were the words “Document Reference AA3553” being an incorporation by reference of Memorandum of Common Provisions AA3553 whose provisions included:
      1. “Secured Money” was defined to include: (a) the Advance; (d) all amounts that are or may become owing to the Mortgagee under any agreement between the Mortgagor and the Mortgagee now or in the future (cl. 11.1);
      2. The Mortgagor promised to pay all the Secured Money to the Mortgagee (cl. 1.2(a));
      3. The Mortgagor was entitled to a discharge when all the Secured Money was paid and the Mortgagee was reasonably satisfied that it would not have to repay anything and that the Mortgagee did not have any contingent liability (cl. 2.6(b));
      4. the Mortgagor must pay the Mortgagee the Secured Money in accordance with this mortgage (cl. 5.2(a)).
  • On 24 February 2021 a sequestration order was made against the estate of Sassine and the plaintiff was appointed as the trustee of his bankrupt estate.
  • On 1 March 2021 Lennon registered the mortgage.
  • On a number of occasions from February to December 2021 the plaintiff attempted, invoking ss. 77A, 90 and 91 of the Bankruptcy Act, to obtain extensive information and documents from Lennon about his asserted security interest and the affairs of the bankrupt. Lennon did not respond to the plaintiff for many months and when he did, on 18 June, the response was less than complete, being provision of the charge, mortgage and mortgage form lodged with PEXA on 24 February 2021.  He did not provide any details of any fee agreement, work, invoices, payments, mortgage balance, valuation, or related documents.  Pursuant to s. 77C of the Bankruptcy Act the Australian Financial Security Authority sought similar information to that sought by the plaintiff, with no response.
  • In June 2022 the plaintiff commenced this proceeding seeking a declaration that the mortgage was invalid and for orders removing it and the caveat from the certificate of title of the Land.
  • Lennon swore an affidavit on 22 November 2022 to which (as an exhibit) he produced the costs agreement for the first time. The final paragraph of the affidavit read –

    “At the date of swearing this affidavit, LL is owed substantial fees for the provision of legal services which I believe to be in the order of at least $40,000.  The costs include the costs necessary to defend this proceeding.  The legal work necessitated by the difficulties the Sassine family have encountered are ongoing.”

Barrett AsJ. dismissed the proceeding, holding –

  1. The charge was “an agreement” as described in the caveat, notwithstanding that it recited that Lennon Lawyers not Lennon had provided and would provide services, as Lennon was the legal entity carrying on business under that business name. The use of the business name in the charge did not render it incapable of supporting the caveat. [37], [45]
  2. The costs agreement was not binding because –
      1. Although its provision for acceptance was consistent with cl. 180(3) of the Legal Profession Uniform Law (Vic) (LPUL) there was no evidence that the clients had accepted the offer, whether by signing and returning the document or by continuing to give instructions. The final paragraph of Lennon’s affidavit was insufficient: its first sentence did not state who owed the fees or pursuant to what agreement, if any; its last sentence did not identify whether Lennon had been retained to perform any work and if so, what or pursuant to what, if any, retainer. [49]-[51]
      2. The fact that Lennon did not produce a signed copy of the costs agreement, or written instructions or file notes of such instructions constituting acceptance of it, supported the inference that he did not have them. [55]
      3. Clause 174(3) of the LPUL required the solicitor to take all reasonable steps to satisfy himself that the client had understood and consented to the proposed course of action for the conduct of the matter and the proposed costs. There was no evidence of this. [52]-[53]

Accordingly, Lennon had not discharged the onus of establishing that the costs agreement was entered into or that legal services were provided pursuant to it. [55]

  1. As to documents requested in a notice under s 77A of the Bankruptcy Act sent on 20 April 2021, Lennon neither produced them nor stated whether had had them, permitting the inference that he did not have them and consequently that neither the charge or mortgage secured any monetary amount owing. [55]
  2. However, the charge supported a caveatable interest notwithstanding the lack of a binding costs agreement.  More particularly –
    1. The charge did not purport to secure the provision of any costs that may be identified by, or referable to, any particular costs agreement alone, but rather, secured the costs of such legal services as may be provided to the extended Sassine family and related entities. A charge could validly, before any particular retainer, not secure an extant monetary liability but be a security available to be employed between the parties in accordance with their agreement. [37], [56], [57]
    2. The term in the charge permitting Lennon Lawyers to lodge a caveat supported the caveat. Unless there was evidence of an intention to the contrary, the grant (by a borrower to its creditors) of an authority to lodge a caveat implied the grant of an estate or interest in the land affected by the caveat sufficient to resist its removal. [57]
    3. The recovery of legal fees did not depend upon the existence of a valid and enforceable fee agreement: an agreement not satisfying the LPUL may be void (cl. 178(1)(a)) but the client may still have to pay costs once assessed or the subject of a determination of a costs dispute by the designated local regulatory authority (cl. 178(1)(b)). [58]

    [59]

  1. It was not a requirement of validity of a charge or other security that it secure a sum certain liability, eg an “all moneys” mortgage (such as the mortgage here) could secure potential legal fees up to a particular sum. It was accordingly permissible for the charge to stipulate that the firm would provide the Services up to the value of $100,000. [16], [37], [61]
  2. There was accordingly at least some probability that the caveator would be found to have the equitable rights or interest in the land asserted in the caveat sufficient to justify the practical effect of the caveat on the ability of the plaintiff to deal with it. [63]
  3. The balance of convenience favoured maintenance of the caveat. The prejudice occasioned to the caveator by removal outweighed the prejudice to the plaintiff by maintenance of the caveat because removal would occasion: the loss of the security for payment of fees incurred in accordance with the terms of the charge; the mortgage (for reasons stated below) prevented the plaintiff dealing with the title anyway; and the plaintiff could still seek partition of the co-ownership or redemption of the mortgage. [64], [65]
  4. The mortgage was expressed as security “for the debt or liability described in the terms and conditions set out or referred to in this mortgage”, and, although no debt or liability was specified in the mortgage document itself, the terms in the Memorandum of Common Provisions including particularly cl 11.1 rendered this an “all moneys” mortgage.  “All monies” clauses were to be construed in light of the language used and having regard to the context of the mortgage and its commercial purpose.  There was no reason to read this clause down to exclude any future liability resulting from any of the Sassine family or related entities engaging Lennon to provide legal services as described in the charge. [38], [68] – [70], [72]
  5. When all amounts owing under the mortgage had been paid the mortgagor was entitled to redemption, if necessary by compelling the mortgagee to provide a discharge of the mortgage. Where a mortgagor became bankrupt, the trustee had rights under s. 136 of the Bankruptcy Act to redeem. [74], [76]
  6. Proceedings between tenants in common of mortgaged property could not affect the mortgagee’s interest in the entirety, and so, if a co-tenant mortgagor obtained partition, the mortgage would affect each severed portion, and a co-tenant, or the trustee in bankruptcy of a co-tenant, wishing to redeem a mortgage must redeem it entirely. Given Lennon’s failure to provide information the plaintiff understandably had not offered to redeem, but this was not a basis for declaring the mortgage invalid or to discharge it on the application of the trustee in bankruptcy of only one tenant in common. [76], [77]

Philip H. Barton

          Owen Dixon Chambers West

        Tuesday, November 28, 2023

Blog 77. No prima facie case of a contract of sale.

Ritz Bitz Pty Ltd & Anor v Cumming & Ors [2023] VSC 418, M. Osborne J.

This is the longest Blog because of the complexity of the facts and the desire of the registered proprietors to amend their Defence substantially.  This case largely concerns whether there was a prima facie case that a contract of sale existed.  An interesting twist is how his Honour dealt with misdescription in the caveat of the claimed interest in land.   Undisputed evidence was given that this was due to the PEXA options.  M. Osborne J. stated that this misdescription “would be put to one side” and did not consider possible amendment of the caveat, but noted that the caveator could have sought an interlocutory injunction which in practical terms would have secured the same outcome (but nonetheless the case remained one of caveat removal).  This appeared in turn to lead to some greater consideration than usual in a caveat case of the necessity and value of the undertaking as to damages offered.

The facts were as follows –

  • The defendants Daniel and Amanda Cumming (the couple) were registered proprietors of a property in Footscray improved by a former dance hall (the Property), at which as at mid 2015 his mother lived.
  • Daniel’s brother John was the second plaintiff and controlled the first plaintiff (Ritz Bitz).
  • In about 2015 the brothers discussed possible subdivision of the Property and the sale of part of it to John.  John alleged that an oral contract was made at this time to sell to him that part of the Property “later known as lot 1” (Lot 1) on a particular plan of subdivision (the 2015 contract).
  • In August 2015 John purchased a property in Braybrook, where their mother then lived, registered in the names of siblings of the brothers.
  • In early 2016 (John subsequently deposed) it was agreed, at Daniel’s request, to change the proposed two lot subdivision to a three lot subdivision, with John bearing one third and the couple bearing two thirds of the costs (the one third/two thirds agreement).
  • On about 22 August 2016 a plan for a three lot subdivision was lodged with the local Council. On 23 August 2016 it advised that it would approve the plan of subdivision, subject to compliance with requirements principally concerning fire safety including provision of a fire safety report.
  • In 2017 John proffered a standard form of contract for the sale of Lot 1, which the couple refused to sign.
  • In 2019 John obtained a fire safety report. By this time the Property was largely vacant and dilapidated.
  • In 2020 the Braybrook property was sold.  The proceeds of sale were paid to the plaintiffs.
  • In April 2022 John caveated over the Property claiming an implied, resulting or constructive trust. In September the Council issued a building order for minor work requiring compliance that month.  On 10 December Daniel and Amanda entered a contract of sale of the Property to a third party, Nikolce Talevski, under which the deposit was paid, due for settlement in February 2023.  Settlement had not occurred.
  • In December 2022 the plaintiffs commenced a proceeding against the couple and, because of other transactions not presently material, a company controlled by Daniel. The pleadings were a Statement of Claim and Defence which the defendants subsequently sought leave to amend.  The relevant pleadings were broadly:
    • The Statement of Claim paragraph 52 pleaded that in about July 2015 the couple agreed to sell to John part of the Property later known as lot 1 a particular plan of subdivision for $2 m. “on vendors terms”. The agreement was particularised as oral and implied, insofar as oral being contained in discussions between the John, the couple, and their mother at the Croatian Club in Footscray.  The Defence admitted this allegation but leave was sought to amend the Defence to deny this allegation and also plead: (a) that although John had at about that time offered to purchase lot 1 on a proposed plan of subdivision for $2 m. the offer was on terms including that: (i) he would arrange and pay for lodgment of the plan of subdivision (the “condition precedent”); (ii) he would pay a deposit of $800,000 to the couple to enable them to purchase a property at which their mother could live; (iii) the balance of the price would be paid within 12 months of entry into a contract; (b) the condition precedent was never fulfilled because the plan of subdivision was rejected by the Council for want of a fire safety plan; (c) non-compliance with s. 126 of the Instruments Act.
    • Paragraph 53 of the Statement of Claim alleged that on or about 22 August 2016 the Council advised the couple that the plan of subdivision had been lodged and that lot numbers had been allocated. However, paragraph 55 pleaded that on 23 August 2016 the Council advised that subject to its requirements (principally directed at fire safety) it would “give agreement for the plan of subdivision to be lodged”.  The Defence admitted these paragraphs but in paragraph 55 went on to plead “that upon the issue of the [requisite fire report] to John in 2019 he decided not to proceed with the purchase”.    The Defence also pleaded that the subdivision was not approved “by council as per the council’s requirement for the fire safety report to be provided”.
    • The Statement of Claim paragraph 56 pleaded that the terms of the contract included that: (a) the price for Lot 1 would be $2 m.; (b) the deposit was $800,000, to be paid in kind “by John providing a property for his mother to live in (she then residing at the … Property)”; (c) the balance of the price was to be paid on terms, with John developing a backpackers hostel at Lot 1 and to pay $1.2 m. 12 months after its establishment; and (d) that John would be responsible for obtaining planning permits and procuring registration of the plan of subdivision.
    • The Defence admitted the allegations in paragraphs 56(a), (b) and (d). It did not admit the allegations in paragraph 56(c) and added that it was a term that the balance of price was payable within 12 months, subject to approval of the plan of subdivision, and there was no agreement concerning a backpackers hostel.  Leave was sought to amend the Defence to: plead that no contract was ever formed and replace the admission of paragraph 56(a) with a denial, adding that John agreed to pay a deposit of $800,000 in cash to the couple so that the couple could purchase a property in which their mother could reside.
    • The Statement of Claim paragraph 57 pleaded that the alleged vendors represented and warranted that “part of the purchase price being $800,000 should be paid in kind by John purchasing a property for John and Daniel’s mother such that she would have a place to live” and that in reliance upon the representations, John acquired the Braybrook property for his mother. Paragraph 58 of the Defence pleaded that John had purchased the Braybrook property for $665,000, being less than the agreed deposit of $800,000, and had subsequently used it as security for Ritz Bitz to purchase a hotel.  It was sought to amend the Defence to add (paragraph 58(a)) that the $800,000 was to be paid in cash to the couple, and that John had since sold the Braybrook property and applied the proceeds to his own use.
    • The Statement of Claim paragraph 60 pleaded that in 2017 John proffered a draft contract of sale to Daniel and Amanda to give effect to the 2015 contract. The Defence pleaded that they did not sign it because it “was completely different to the original offer”.
    • The Statement of Claim paragraph 62 pleaded that the couple had breached the contract because they had “failed to convey [lot 1] to John upon payment of $1.2 million”.
    • Specific performance was sought of the 2015 contract requiring the plan of subdivision to be registered (and for the couple to do all that was necessary to register the plan) and for Lot 1 to be transferred to John upon his payment of $1.2 m. to the couple.
    • The Statement of Claim did not advert to any agreement to share the costs of a contemplated two lot subdivision equally, or of any agreement to split the costs of a contemplated three lot subdivision, but his Honour noted that the most logical reading of the pleading was that John was to bear the costs.
  • In June 2023 the Council served an emergency order on the couple requiring vacation of the building and performance of demolition works by 21 June. Daniel subsequently deposed that the couple lacked the resources to undertake these works.
  • The defendants applied under the Transfer of Land Act s. 90(3) for removal of the caveat and for leave to amend their Defence and Counterclaim.
  • John argued that his interest did not arise under an implied, resulting or constructive trust but was that of a purchaser under the 2015 contract. His solicitor deposed that those words were used in the caveat because when it was lodged John could not recall (and thereby nominate) the exact date in July 2015 of the contract, which inability meant that the only PEXA option for the grounds of claim was that nominated.  This evidence was not challenged.
  • John deposed –
    • to a conversation with his mother before and to similar effect as that at the Croatian Club referred to in the Statement of Claim in which he offered $2 m. to her for the front half of the Property (the Property being, according to John, in fact his mother’s property, notwithstanding that it was registered in the names of the couple), that he agreed to pay $800,000 immediately to her which she could use to acquire a property to live in, and that he would then pay her the balance of $1.2 million once the property was operating as a backpackers hostel;
    • that “as part of the relief [to be obtained in the proceeding he] will also need to pay over the ‘deposit’ from the sale of the Braybrook Property”;
    • to an agreement to change the proposed two lot subdivision to a three lot subdivision, on the basis of the one third/ two thirds arrangement;
    • that he believed that the value of Lot 1 was significantly above $2 m.
  • John exhibited to certain emails to his affidavit.
  • Daniel exhibited to his affidavit a copy of the written contract provided by John, which was largely inconsistent with the alleged 2015 contract. Although John deposed that the contract provided by him in 2017 was not inconsistent with the alleged 2015 contract he did not depose that the document exhibited by Daniel was not the contract provided.  However John’s counsel stated from the Bar table that his instructions were that the document exhibited by Daniel was not the contract provided in 2017, and that John no longer had a copy of it.
  • Daniel and Amanda tendered a fire engineering report dated 5 March 2019.
  • The plaintiffs offered an undertaking as to damages.

M. Osborne J. ordered removal of the caveat, holding –

  1. The misdescription in the caveat of the grounds of claim would be put to one side because the true alleged interest had been asserted in a solicitor’s letter and, even if the court had not had power (which it did have) to amend the caveat, the caveator could have sought an interlocutory injunction to restrain settlement of the third party sale which in practical terms would have secured the same outcome. [34]-[35]
  2. Although completion of the alleged 2015 contract was conditional on registration of the plan of subdivision, and thus on consent of a third party, a court would, in appropriate circumstances, make orders in the nature of specific performance compelling the vendor to do what was necessary to obtain approval for the subdivision and, if approval was granted, to settle the contract. This interest was sufficient to support a caveat. [36]-[38]
  3. There was not a prima facie case that a contract existed, because even allowing for the admissions in the Defence, the contract as alleged was attended with difficulty, as follows –
    1. The Statement of Claim lacked precision, in particular:
      1. the allegation that the subject matter of sale was land later known as a particular lot number on a plan of subdivision could not accurately reflect the particularized July 2015 discussions, because this plan was not yet prepared; [43]
      2. notwithstanding consensus in the pleadings that the plan was uncertified because Council’s fire safety requirements remained unaddressed, the Statement of Claim did not directly engage with the fact that settlement was impossible pending certification and subsequent registration of the plan, nor with what was necessary to procure certification or with who was responsible for securing certification and registration; [44]-[45]
      3. the reference in paragraph 52 to “vendors terms”, unidentified and unclear, seemed to suggest settlement at an undefined point not linked to registration of the plan; [46]
      4. the allegation in paragraph 62 that the alleged vendors had breached the contract by failing to convey Lot 1 to John upon payment of $1.2 m.: did not reflect that the obligation to convey was dependent on registration, did not plead tender of this sum, and did not clarify how reference to this sum was reconciled with the sale on the ‘vendors terms’, whatever they might be; [46]
      5. The pleas concerning the deposit and its payment were unclear; [47]
      6. The relevance of the allegations in paragraph 57 were unclear: they appeared to set the scene for pleas of estoppel or part performance without following through; [48]
      7. A fair, but not the only, reading of the Statement of Claim was that the deposit of $800,000 was to be paid in kind. However, the question of who was to own the Braybrook property was left unsaid, much less how the purchase of a property otherwise than for the couple could amount to part performance of an obligation to pay them $2 m. for Lot 1; [49]
      8. The relevance of the provision of the later written contract to the claim for specific performance was unclear, and that document contained myriad inconsistencies with the alleged 2015 contract. [50], [53]
    2. John’s evidence of a conversation with their mother in which he offered her $2 m. for the front half of the Property was inconsistent with his pleading that $1.2 m. was be paid to the couple. [57]
    3. In broad terms, the emails exhibited by John supported an interpretation of the 2015 contract as containing a term that payment the deposit of $800,000 was to be effected in some way by the purchase of a property for their mother. [58]
    4. Notwithstanding the purchase of the Braybrook property for their mother and its registration in the names of the brothers’ siblings the plaintiffs received the proceeds of sale. Although the Statement of Claim sought an order in effect requiring the transfer of Lot 1 to John upon his payment to the couple, he had deposed that “‘as part of the relief, [he] will also need to pay over the ‘deposit’” from this sale, thus implicitly recognising that the couple were entitled to the $2 m., which was not the same as part of the $2 m., namely the $800,000 ‘deposit’, being paid to their mother to buy the Braybrook property and was inconsistent with the plaintiffs’ ultimate receipt of the proceeds of sale.  On the case that John now sought to advance, the couple, not John (or his mother’s estate), were entitled to the $800,000. [59]
    5. It was undisputed that responsibility for obtaining registration of the plan of subdivision, fell on John not, as was usual, on the vendors. And, although John deposed to an agreement to change the proposed two lot to a three lot subdivision, he had not pleaded this agreement nor one to share the costs equally on the basis of a contemplated two lot subdivision. [60]
    6. In summary, even if the court was to assess the question of a prima facie case by reference to the alleged admissions in the Defence, there were significant impediments to the establishment of a legally binding contract in the form of the alleged oral 2015 contract. In particular:
      1. The alleged 2015 contract failed sufficiently, arguably at all, to take account of the sale being conditional because dependent upon certification and registration and was entirely unclear on the date of payment of the price or whether this payment was conditional. [62]
      2. The only form of written contract in evidence was quite inconsistent with the alleged 2015 contract, or with the parties becoming legally bound before its execution, and as John had not deposed that the document in evidence was not the document proffered no weight could be attributed to his instructions conveyed from the Bar table to the contrary. [63]
      3. As to the deposit, the Statement of Claim was most unclear. It was ambiguous as to whether John would pay $800,000 to the vendors (suggested by the pleading and the relief which John now accepted he would be entitled to at final hearing) or whether (as pleaded in paragraph 57(c)) it be paid in kind by John purchasing a property for their mother (and so suggestive of the $800,000 being paid in effect to their mother) which was consistent with the version in John’s affidavit.  Whatever the true interpretation, it was difficult to see how John could have paid the $800,000 deposit, whether to his mother, or to the couple by being used to buy a house for their mother  (which presumably meant that the couple did not have to do so), but still somehow received the proceeds of sale of the Braybrook Property. [64]

      [42], [61], [65]

  1. The question of the prima facie case was not confined to whether there was a binding sale agreement for Lot 1 but extended to whether specific performance would be granted for the sale of a lot in a plan of subdivision which remained unregistered some 8 years after the date of the alleged contract. As to this:
    1. Contracts for the sale of lots in unregistered plans of subdivision were amenable to orders for specific performance because of the normal implied term requiring the vendor to do everything reasonably necessary to procure registration. However, here John bore the burden of obtaining registration. [67]
    2. Even if the court was to accept for the purposes of this Application that (although unpleaded) the contract had been varied to change the proposed two lot to a three lot subdivision with the one third/two thirds arrangement, there was uncertainty about the costs, nature and extent of the required tasks. The report tendered was long and required performance of a range of measures to attain certification of the plan of subdivision.  And it appeared in 2023 that further works would be required.  In sum, the works required were complex, unidentified, and at some indeterminate and potentially large cost, to be met on John’s case as to one third by him and two thirds by the couple. [68], [70], [71]
    3. Accordingly, a series of further orders for their performance and payment would be required antecedent to any order for specific performance. Although a court would supervise a contract the performance of which required costs to be met in agreed proportions, in this case the costs related to, at least in part, performance of building works of uncertain scope. A building agreement was one requiring continual supervision in respect of which a court was reluctant to grant orders for specific performance.  If specific performance were granted the court would  likely have to supervise potentially significant building works not yet identified or delineated by the alleged 2015 contract. [72], [73], [78]
    4. John had also failed to establish a prima facie case that he was ready, willing and able to perform the obligations imposed on him by the alleged 2015 contract. Even assuming in his favour that his non-payment of a deposit in the traditional sense was not itself a disentitling breach of contract, he had led insufficient evidence of ability to meet future necessary payments. [74]-[78]

    [66]

  1. In conclusion John has not established a prima facie case at a sufficient level of certainty to justify the maintenance of the caveat. [78]
  2. The balance of convenience also favoured removal of the caveat. Ordinarily, because contracts for the sale of land were the subject for orders for specific performance, land being of a unique character such that damages were not an adequate remedy, the balance of convenience favoured a caveator with a prima facie case and priority over any relevantly competing interest.  However here the balance of convenience was against John because:
    1. Of his Honour’s concerns about the adequacy of the undertaking as to damages offered by Ritz Bitz and John – the insufficiency of an undertaking as to damages being a powerful discretionary factor against the grant of an interlocutory injunction – there being a very real possibility that the couple would suffer significant losses by reason of their inability to settle the third party contract; [82]-[84]
    2. If the caveat remained in place the Property would likely deteriorate or the couple would have to finance rectification works in order to deal with the building order and the emergency order or face prosecution; [88]
    3. Talevski’s interests would be effected; [89]
    4. Notwithstanding John’s emotional connection with the Property he had not pursued his claim with alacrity and if his assessment that Lot 1 was worth substantially more than $2 m. this would sound in damages. [90]

    [80], [91]

    Philip H. Barton

              Owen Dixon Chambers West

            Tuesday, December 5, 2023